Construction Engineering & Management

CPM scheduling, earned value, earthwork, equipment production, safety. approx. 8–12%

About 4 min read · 11 sections

Overview

Construction engineering and management covers scheduling, cost control, equipment production, earthwork and safety. FE questions are short: a critical-path network, an earned-value index, a production rate, or an OSHA rule. Practise drawing the network and keeping bank, loose and compacted volumes separate.

1. Critical path method (CPM)

Draw the network. Do a forward pass to find each activity's earliest start (ES) and earliest finish (EF = ES + duration), then a backward pass for latest finish (LF) and latest start (LS = LF − duration).

Total float TF = LS − ES = LF − EF

Activities with zero float form the critical path, the longest path, which sets the project duration. Free float is the delay possible without delaying the next activity's early start.

Small network

Given: A (3 d) is first. B (4 d) and C (2 d) both follow A. D (5 d) follows B and C.

Solution: forward pass: A: ES 0, EF 3. B: ES 3, EF 7. C: ES 3, EF 5. D: ES 7 (the later of 7 and 5), EF 12. Project duration is 12 days. Critical path A–B–D. Float of C = 7 − 5 = 2 days.

2. Crashing and time–cost trade-off

To shorten a project, crash the critical activity with the lowest cost slope.

Cost slope = (crash cost − normal cost)/(normal time − crash time)

Cost slope

Given: normal 10 d for $5,000; crash 8 d for $6,200.

Solution: slope = 1,200/2 = $600 per day.

Remember that crashing a non-critical activity does not shorten the project, and the critical path may change as you crash.

3. Earned value management

Three baseline numbers: planned value PV, earned value EV (budgeted cost of work done) and actual cost AC.

CPI = EV/AC, SPI = EV/PV, CV = EV − AC, SV = EV − PV
EAC = BAC / CPI, ETC = EAC − AC, VAC = BAC − EAC

Indices below 1.0 mean over budget or behind schedule.

Earned value

Given: BAC = $1,000,000, EV = $400,000, AC = $500,000, PV = $450,000.

Solution: CPI = 0.80 and SPI = 0.89. EAC = 1,000,000/0.80 = $1,250,000. ETC = $750,000. VAC = −$250,000.

4. Estimating and economics

A bid starts with quantity take-off, unit prices for labor, materials and equipment, then overhead and profit. Labor cost per unit = (crew hourly cost)/(production per hour). Break-even quantity = fixed cost/(price − variable cost).

Labor unit cost

Given: a crew of 3 at $40/hr each places 120 ft²/hr.

Solution: $120/hr ÷ 120 ft²/hr = $1.00 per ft².

5. Equipment and earthwork

Production = capacity × cycles per hour × efficiency. Cycles per hour = 3,600/cycle time (seconds); a 50-minute hour is an efficiency of 0.83.

Excavator production

Given: a 2 yd³ bucket, 30 s cycle, 50-min hour.

Solution: cycles = 3600/30 = 120 per hour. Production = 2(120)(0.833) = 200 loose yd³/hr.

Soil volume changes by condition. Swell: loose volume = bank volume × (1 + swell). Shrinkage: compacted volume = bank volume × (1 − shrinkage).

Swell and shrinkage

Given: 1,000 bank yd³ with 25% swell and 15% shrinkage.

Solution: loose = 1,250 yd³ (what trucks haul); compacted = 850 yd³ (what fills the embankment).

Concrete quantity: volume in ft³ ÷ 27 = yd³. A 40 ft × 30 ft slab 6 in thick is 600 ft³ = 22.2 yd³.

6. Safety (OSHA)

  • Fall protection: required at unprotected edges 6 ft or more above a lower level in construction (4 ft in general industry).
  • Trenching: a protective system (sloping, shoring or shielding) is required at 5 ft or deeper, unless the trench is in stable rock; a competent person inspects daily; a ladder or ramp must be within 25 ft of workers in a trench 4 ft or deeper.
  • Hazard communication, PPE and scaffolding rules also apply; the hierarchy of controls favors eliminating the hazard first.

7. Contracts and delivery

ContractWho carries cost risk
Lump sumcontractor
Unit priceshared; owner for quantity changes
Cost-plusowner
Guaranteed maximum pricecontractor above the cap

Delivery methods: design–bid–build, design–build and construction manager at risk. Bid, performance and payment bonds protect the owner and subcontractors.

Common mistakes

  • Using the wrong volume state (bank, loose, compacted).
  • Taking the shorter path through a merge as the critical path.
  • Forgetting that float is zero on the critical path only.
  • Using EV/PV for cost and EV/AC for schedule (reversed).
  • Mixing the OSHA heights for construction and general industry.

Exam strategy

Draw the network and list ES, EF, LS and LF in a table. For earned value, write the three baselines and compute each index separately. For production, write units through the calculation.

Checklist

  • [ ] I can run a forward and backward pass and find float.
  • [ ] I can compute CPI, SPI, EAC and VAC.
  • [ ] I can find equipment production and soil volume changes.
  • [ ] I know the key OSHA heights and trench rules.
  • [ ] I can compare contract types by risk.