Reference
Formula sheet
Quick-reference equations grouped by topic. On exam day use the official NCEES reference materials — this sheet is for fast review and recall.
Mathematics FE
- Product rule
- (uv)' = u'v + uv'
- Eigenvalues
- det(A − λI) = 0
- First-order ODE
- y' + ky = 0 → y = y₀ e^(−kx)
- Dot product
- A·B = AxBx + AyBy + AzBz
Probability & Statistics FE
- Sample std dev
- s = √[ Σ(x − x̄)² / (n − 1) ]
- z-score
- z = (x − μ)/σ
- Binomial
- P(X=k) = C(n,k) pᵏ (1−p)ⁿ⁻ᵏ
- CI (σ known)
- x̄ ± z·σ/√n
Engineering Economics FE
- Future worth
- F = P(1 + i)ⁿ
- Capital recovery
- A = P · i(1+i)ⁿ / [(1+i)ⁿ − 1]
- Annuity PW
- P = A · [(1+i)ⁿ − 1] / [i(1+i)ⁿ]
- Effective rate
- i_eff = (1 + r/m)ᵐ − 1
- Straight-line depreciation
- D = (C − S)/N
Statics FE
- Equilibrium
- ΣFx = 0, ΣFy = 0, ΣM = 0
- Moment
- M = F · d (perpendicular distance)
- Static friction
- F ≤ μₛ N
- Uniform load resultant
- R = wL at L/2
Dynamics FE
- Kinematics
- s = v₀t + ½at²
- Work–energy
- W = ½m(v₂² − v₁²)
- Normal acceleration
- aₙ = ω²r = v²/r
- Natural frequency
- ωₙ = √(k/m)
- Impulse–momentum
- FΔt = mΔv
Mechanics of Materials FE
- Axial stress / elongation
- σ = P/A, δ = PL/(AE)
- Flexure
- σ = Mc/I, I(rect) = bh³/12
- Torsion (solid)
- τ = 16T/(πd³)
- Euler buckling
- P_cr = π²EI/(KL)²
- Max in-plane shear
- τ_max = √[((σx−σy)/2)² + τxy²]
Thermodynamics FE
- First law (closed)
- Q − W = ΔU
- Ideal gas
- Pv = RT, R(air) = 0.287 kJ/kg·K
- Carnot
- η = 1 − T_L/T_H
- Refrigerator COP
- COP = Q_L / W
- Entropy
- ΔS = Q/T (reversible, constant T)
- Sensible heat
- Q = m c ΔT
Fluid Mechanics FE
- Hydrostatic pressure
- P = ρ g h
- Continuity
- Q = A v
- Bernoulli
- P/γ + v²/2g + z = const
- Reynolds number
- Re = ρ v D / μ
- Darcy–Weisbach
- h_f = f (L/D) (v²/2g)
- Buoyancy
- F_B = ρ g V
Electrical Circuits FE
- Ohm / Power
- V = IR, P = I²R
- Parallel (2 R)
- R_eq = R₁R₂/(R₁ + R₂)
- Divider
- V_out = V_in R₂/(R₁ + R₂)
- RC time constant
- τ = RC
- Reactance
- X_L = 2πfL, X_C = 1/(2πfC)
- Impedance
- |Z| = √(R² + X²)
Materials Science FE
- FCC / BCC APF
- FCC 0.74, BCC 0.68
- Eutectoid (Fe–C)
- 0.77 wt% C at 727 °C
- Hooke
- σ = Eε
- Engineering strain
- ε = ΔL/L₀
Chemistry FE
- Moles
- n = m / M
- Molarity
- M = n / V(L)
- pH
- pH = −log[H⁺]
- Ideal gas
- PV = nRT, R = 0.08206 L·atm/mol·K
Surveying FE
- Height of instrument
- HI = Elev + BS; Elev_new = HI − FS
- Interior angle sum
- Σ = (n − 2) · 180°
- Curve tangent
- T = R tan(Δ/2)
- Curve length
- L = R Δ (radians)
- Long chord
- LC = 2R sin(Δ/2)
- Vertical curve K
- K = L / A
- Average end area
- V = L (A₁ + A₂) / 2
Hydrology & Hydraulics FE
- Rational method
- Q = C i A
- SCS storage
- S = 1000/CN − 10
- SCS runoff
- Q = (P − 0.2S)² / (P + 0.8S)
- Manning (SI)
- V = (1/n) R^(2/3) S^(1/2)
- Critical depth (rect.)
- y_c = (q²/g)^(1/3)
- Darcy
- Q = K i A
Environmental Engineering FE
- BOD exerted
- BOD_t = L₀ (1 − e^(−kt))
- Mixing
- C = (Q₁C₁ + Q₂C₂)/(Q₁ + Q₂)
- Detention time
- t = V / Q
- Overflow rate
- v₀ = Q / A
- Hardness
- mg/L as CaCO₃ = mg/L ion × 50/EW
Structural Analysis FE
- Truss determinacy
- m + r = 2j
- SS beam point load
- M = PL/4, Δ = PL³/(48EI)
- Cantilever end load
- M = PL, Δ = PL³/(3EI)
- Fixed-end moment
- FEM = wL²/12
- Stiffness
- k = 4EI/L (fixed far end), 3EI/L (pinned)
Structural Design (Steel & Concrete) FE
- LRFD vs ASD
- U = 1.2D + 1.6L | ASD: D + L
- Tension yielding
- φP_n = 0.9 F_y A_g
- Plastic moment
- M_p = F_y Z_x, φM_n = 0.9 M_p
- Concrete modulus
- E_c = 57,000 √f′_c (psi)
- Concrete shear
- V_c = 2 √f′_c b_w d (psi, in)
- Reinforcement ratio
- ρ = A_s / (b d)
Geotechnical Engineering FE
- Saturation relation
- S e = w G_s
- Dry unit weight
- γ_d = γ / (1 + w)
- Effective stress
- σ′ = σ − u
- Mohr–Coulomb
- τ = c′ + σ′ tan φ′
- Earth pressure
- K_a = tan²(45° − φ/2), K_p = 1/K_a
- Consolidation time
- t ∝ H_dr²
Transportation Engineering FE
- Stopping sight distance
- SSD = 1.47Vt + V²/[30(f ± G)]
- Flow
- q = k · v
- Greenshields max flow
- q_max = v_f k_j / 4
- Peak-hour factor
- PHF = V / (4 V₁₅)
- Curve
- e + f = V² / (15 R)
- Webster cycle
- C = (1.5L + 5)/(1 − Y)
Construction Engineering & Management FE
- Total float
- TF = LS − ES = LF − EF
- Cost performance index
- CPI = EV / AC
- Schedule performance index
- SPI = EV / PV
- Swell
- V_loose = V_bank (1 + swell)
- Production
- P = capacity × (3600/t_cycle) × efficiency
Construction Materials: Concrete, Aggregate & Asphalt FE
- Water–cement ratio
- w/c = W_water / W_cement
- Compressive strength
- f′_c = P / A
- Absorption
- (SSD − OD) / OD × 100
- Fineness modulus
- FM = Σ cum. % retained / 100
Hydrology & Open-Channel Hydraulics PE
- Rational method
- Q = C i A
- Manning (US)
- V = (1.49/n) R^(2/3) S^(1/2)
- Froude number
- Fr = V / √(g · A/T)
- Rect. weir
- Q = 3.33 L H^(3/2)
Geotechnical Engineering PE
- Effective stress
- σ′ = σ − u
- Dry unit weight
- γ_d = G_s γ_w / (1 + e)
- Consolidation settlement
- S = C_c H/(1+e₀) · log[(σ′₀+Δσ)/σ′₀]
- Rankine active
- K_a = tan²(45° − φ/2), P_a = ½K_aγH²
Structural Analysis & Design PE
- LRFD gravity
- U = 1.2D + 1.6L
- SS beam, uniform
- M = wL²/8, Δ = 5wL⁴/(384EI)
- RC stress block
- a = A_s f_y /(0.85 f′_c b)
- Nominal moment
- M_n = A_s f_y (d − a/2)
Three-Phase Systems, Transformers & Machines PE
- 3φ real power
- P = √3 V_L I_L cosθ
- Wye
- V_L = √3 V_ph
- Referred impedance
- Z′ = a² Z
- Sync speed
- n_s = 120 f / P
- Slip
- s = (n_s − n)/n_s
Power Factor, Per-Unit & Fault Analysis PE
- PF correction
- Q_c = P(tanθ₁ − tanθ₂)
- Z base
- Z_base = V_base² / S_base
- Fault MVA
- MVA_f = S_base / Z_pu
- Fault current
- I_f = S_f / (√3 V_L)
Heat Transfer & Thermal Cycles PE
- Conduction
- q = k A ΔT / L
- Convection
- q = h A (T_s − T_∞)
- Radiation
- q = ε σ A (T_s⁴ − T_surr⁴)
- LMTD
- (ΔT₁ − ΔT₂)/ln(ΔT₁/ΔT₂)
- Otto
- η = 1 − r^(1−k)
Pumps, Fans & Fluid Systems PE
- Pump power
- P = ρ g Q H / η
- Affinity
- Q ∝ N, H ∝ N², P ∝ N³
- NPSH available
- (P_atm − P_vap)/γ + z − h_L
- System curve
- H = H_s + K Q²
Machine Design PE
- Bolt stress
- σ = F / A_t
- Gear speed
- n₂ = n₁ N₁/N₂
- Goodman
- 1/n = σ_a/S_e + σ_m/S_ut
- Shaft power
- P = T ω